PMP Practice: Categorize stakeholders
Question 2 of 5 in Engage Stakeholders
Show answer & explanation
Correct answer: Conduct a detailed stakeholder analysis using a power-interest grid to categorize stakeholders by their authority level and concern with project outcomes, then tailor engagement strategies accordingly
Explanation
With 47 stakeholders, limited resources, and conflicting opinions about routing decisions, Dante needs a systematic method to determine which stakeholders require active management versus simple monitoring. A power-interest grid allows him to categorize stakeholders based on two critical dimensions: their ability to impact the project and their level of concern about project outcomes. This creates four quadrants that guide engagement strategy—high power/high interest stakeholders need close collaboration and frequent communication, while low power/low interest stakeholders may only need periodic updates. This analytical approach ensures resources are allocated efficiently and prevents the project manager from either over-engaging stakeholders who need minimal attention or under-engaging those who could significantly impact success. Given the routing conflicts mentioned, identifying which stakeholders have both strong opinions AND the authority to influence decisions is essential for proactive engagement planning.
**Why not A:** Meeting individually with all 47 stakeholders is time-consuming and does not efficiently address the prioritization challenge. With limited communication resources, the PM needs a systematic way to determine who requires intensive engagement before investing time in individual meetings with every stakeholder.
**Why not B:** Treating all stakeholders equally with weekly updates and monthly town halls fails to account for differing levels of influence and interest. Some stakeholders need close collaboration while others only need periodic updates, and a uniform approach wastes resources on over-engagement while potentially under-serving high-impact stakeholders.
**Why not C:** Focusing only on the sponsor and city council members ignores stakeholders who may have significant influence through other channels. The scenario specifically mentions environmental groups and neighborhood associations with strong opinions about pipeline routing, and overlooking these groups could create opposition that derails the project.
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions