PMP Practice: Break Down Scope
Question 12 of 14 in Develop and Manage Project Scope
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Work with the product owner and team to decompose the feature into smaller, independently valuable user stories that can be prioritized and delivered incrementally across sprints
Explanation
In agile environments, large features should be decomposed into smaller, independently valuable increments that can be delivered across multiple iterations. This approach allows the team to deliver value sooner, gather feedback earlier, and adjust priorities based on learning. The collaboration between the product owner and team to identify vertical slices of functionality ensures that each smaller story delivers meaningful value while remaining within the team's capacity. The product owner's concern about value delivery is addressed by ensuring each increment is independently valuable, not by forcing a large feature into a single sprint. This maintains sustainable pace and allows for adaptive planning based on feedback after each delivery.
**Why not A:** Scheduling a technical spike to research the implementation approach delays scope decisions unnecessarily. The team's concern is about feature size, not technical uncertainty. The feature is estimated at 21 points against a 35-point velocity, meaning it fits within a sprint but may crowd out other work. Decomposition addresses the scope concern more directly than research.
**Why not B:** Accepting the product owner's position to keep the feature intact and dedicating a single sprint to it ignores the team's legitimate concern that it is too large. While 21 points fits within 35-point velocity, adjusting all other planned work around one feature reduces flexibility and risks quality if the estimate proves low. Collaborative decomposition is better agile practice.
**Why not D:** Escalating the disagreement to the sponsor is premature for a backlog refinement discussion. The product owner and team can resolve this through collaboration, which is the standard agile practice. Feature decomposition is a routine activity that does not require executive intervention. The PM should facilitate the conversation rather than bypass it through escalation.
Key Concept
This question covers Break Down Scope under Develop and Manage Project Scope (Process).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions