PMP Practice: Recommend a Project Execution Strategy
Question 10 of 15 in Develop an Integrated Project Management Plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Consolidate all stakeholder requirements into a single comprehensive document, identify conflicts, facilitate a workshop with all key stakeholders to negotiate trade-offs and establish prioritized objectives, then develop subsidiary plans that reflect the agreed-upon priorities
Explanation
In predictive project planning with multiple stakeholders having conflicting priorities, the project manager must facilitate collaborative decision-making early in the planning process to establish a unified direction. The most effective approach is to identify the conflicts explicitly and bring stakeholders together to negotiate trade-offs before subsidiary plans are developed. This ensures the integrated project management plan reflects consensus on priorities rather than unresolved tensions. By facilitating a workshop where stakeholders can discuss constraints, dependencies, and business value together, the project manager enables informed trade-off decisions that all parties understand and accept. The closing fact that the project charter authorizes plan development but does not specify conflict resolution confirms the PM must actively facilitate this alignment rather than defer it to the sponsor or handle it unilaterally. This approach creates a coherent integrated plan where all subsidiary plans work together toward agreed objectives rather than pulling in different directions.
**Why not A:** Developing separate subsidiary plans for each stakeholder and asking the sponsor to choose which priorities win creates an adversarial dynamic and abdicates the PM's responsibility to facilitate integration. The sponsor should not have to arbitrate between stakeholders when the PM can bring them together to negotiate trade-offs collaboratively.
**Why not B:** Creating the plan based solely on charter objectives and distributing for review treats stakeholder input as an afterthought. Incorporating feedback only through change control after baseline approval means conflicts surface too late, leading to costly changes and stakeholder dissatisfaction. Integration must happen before baselining, not after.
**Why not D:** Working individually with each stakeholder and balancing requests equally avoids the necessary confrontation of conflicting priorities. Presenting a completed plan at the kickoff meeting deprives stakeholders of the opportunity to negotiate trade-offs together. Without collaborative priority-setting, the plan will contain hidden tensions that surface during execution.
Key Concept
This question covers Recommend a Project Execution Strategy under Develop an Integrated Project Management Plan (Process).