PMP Practice: Determine Critical Information Requirements
Question 6 of 15 in Develop an Integrated Project Management Plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 26 days
Explanation
Using the beta distribution formula for three-point estimation (also called PERT), the expected duration is calculated as: (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6. Substituting the values: (18 + 4 × 24 + 42) ÷ 6 = (18 + 96 + 42) ÷ 6 = 156 ÷ 6 = 26 days. This weighted average formula gives more emphasis to the most likely estimate, making it more realistic than a simple average. Since this activity is on the critical path and will be used for regulatory reporting and contractor bonds, using the proper estimation technique is essential for creating an accurate schedule baseline. The beta distribution method is the standard approach in predictive project planning when dealing with uncertainty in activity durations.
**Why not A:** An expected duration of 25 days does not result from the beta distribution formula. The PERT formula (18 + 4 x 24 + 42) ÷ 6 yields 156 ÷ 6 = 26 days, not 25. This answer may reflect a simple average or a rounding error in calculation.
**Why not B:** An expected duration of 24 days simply uses the most likely estimate without applying the PERT weighted formula. The three-point estimation technique specifically accounts for optimistic and pessimistic scenarios to produce a more realistic weighted average, which is 26 days in this case.
**Why not C:** An expected duration of 28 days is too high and does not result from the correct formula. The calculation (18 + 96 + 42) ÷ 6 = 156 ÷ 6 = 26 days. An answer of 28 might result from an arithmetic error or using an incorrect weighting approach.
Key Concept
This question covers Determine Critical Information Requirements under Develop an Integrated Project Management Plan (Process).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions