Skip to content
PMPMedium

PMP Practice: Assess Plans for Dependencies and Gaps

Chidera Nwosu is managing a warehouse automation project for Ambitious Napkin Inc. The project includes installing robotic sorting systems across four phases. During planning, the team provides the following effort estimates for Phase 2 (conveyor belt integration): Optimistic estimate: 18 days Most likely estimate: 24 days Pessimistic estimate: 42 days Lila needs to calculate a weighted average duration for this phase to support resource planning. The project sponsor has requested that Lila also calculate the standard deviation to understand the variability risk, as Phase 2 is on the critical path and any delay will impact the warehouse opening date. Using the three-point estimation technique, what is the expected duration for Phase 2, and what is the standard deviation?

Key Concept

This question covers Assess Plans for Dependencies and Gaps under Develop an Integrated Project Management Plan (Process).

This is 1 of 100 free PMP questions

Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.

Unlock All Questions