PMP Practice: Keep the Vision Current
Question 15 of 20 in Develop a Common Vision
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitate a collaborative workshop with all three stakeholders to identify shared business outcomes and success metrics that honor both innovation and stability, then co-create a unified vision statement that integrates player value, technical health, and market positioning
Explanation
When stakeholders express competing priorities that create team confusion, the project manager must facilitate collaborative dialogue to uncover the root cause of the misalignment—often differing interpretations of success or unstated concerns. By bringing stakeholders together to identify shared business outcomes (such as sustainable growth, player satisfaction, and competitive positioning), Chidera can help them see how their individual priorities actually support common goals. Co-creating a unified vision ensures buy-in, clarity, and integration across both the iterative and predictive elements of the hybrid approach. This collaborative process breaks down the misunderstanding by surfacing assumptions, finding common ground, and producing a vision that teams can rally behind without contradictory guidance.
**Why not B:** Creating separate visions for different workstreams fragments the project and perpetuates the misalignment rather than resolving it. A hybrid project still requires a unified vision that guides all work—the approach may vary, but the strategic intent must be coherent. This would worsen team confusion about overall priorities.
**Why not C:** While sponsor input is valuable, forcing a binary choice between speed and quality misses the opportunity to find an integrated solution that honors both. This approach also doesn't address the underlying misunderstanding—it imposes a decision rather than building shared understanding. The scenario doesn't indicate the stakeholders' concerns are irreconcilable.
**Why not D:** While understanding stakeholder concerns individually is useful, drafting a document alone and seeking approval doesn't facilitate the shared understanding needed for genuine alignment. This approach risks producing a compromised vision that no one fully supports, and doesn't break down the misunderstanding—it papers over it. The scenario's closing fact (team members actively arguing about conflicting priorities) indicates a collaborative resolution is needed, not a unilateral document.
Key Concept
This question covers Keep the Vision Current under Develop a Common Vision (People).