PMP Practice: Establish Governance Structure and Policies
Question 3 of 11 in Define and Establish Project Governance
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Establish a governance framework that requires compliance review for all releases, but work with the compliance team to create an expedited review track for low-risk features, with clear criteria documented and approved by both the CCO and Product Owner
Explanation
Effective project governance in an agile environment must balance compliance requirements with the need for iterative value delivery. The scenario presents a classic tradeoff between regulatory obligations and agile responsiveness. The best approach establishes governance that honors both constraints through differentiated processes based on risk. By creating an expedited review track for low-risk features with documented criteria agreed upon by both parties, Min-Ji maintains compliance while enabling faster feedback cycles. This collaborative governance model respects organizational policy assets, addresses legitimate regulatory concerns, and preserves agile's value delivery benefits. The closing fact that the sponsor delegated governance decisions to Min-Ji indicates she has the authority to design this framework rather than escalate immediately.
**Why not B:** This approach sacrifices agile's core benefit of rapid iteration and feedback entirely in favor of compliance. While compliance is important, effective governance finds ways to satisfy both needs rather than prioritizing one stakeholder's concern over another without exploring alternatives. The scenario indicates both the 90-day value demonstration and compliance are sponsor expectations, so abandoning rapid delivery would fail to meet project objectives.
**Why not C:** This violates organizational compliance requirements and ethical project management practices. While agile does emphasize working software and customer collaboration, it does not advocate ignoring legitimate regulatory obligations or organizational policies. Choosing to address compliance reactively creates legal and business risk and demonstrates poor governance. The CCO's concerns represent valid organizational constraints that governance must address.
**Why not D:** This prematurely escalates a conflict that the project manager has the authority and capability to resolve. The scenario explicitly states the sponsor delegated governance decisions to Min-Ji, indicating she should design an appropriate framework. Effective project managers establish governance that reconciles competing needs through collaborative problem-solving rather than presenting false dichotomies to executives. These approaches are not fundamentally incompatible—many regulated industries successfully implement agile with appropriate governance.
Key Concept
This question covers Establish Governance Structure and Policies under Define and Establish Project Governance (Business Environment).