PMP Practice: Evaluate engagement needs for stakeholders
Question 1 of 4 in Collaborate with Stakeholders
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitate a joint meeting with both stakeholders to explore options such as phased deployment or parallel testing that could satisfy both timeline and quality requirements
Explanation
When stakeholders have competing legitimate priorities, the project manager's role is to facilitate collaboration to find integrative solutions rather than choosing sides or immediately escalating. Bringing both stakeholders together allows exploration of creative options—such as phased rollout, concurrent testing, or modified scope—that could address both the timeline constraint and quality concerns. This collaborative approach builds trust, demonstrates respect for both perspectives, and often reveals solutions that neither stakeholder considered independently. The project manager adds value by facilitating this dialogue and helping stakeholders understand each other's constraints. Escalation should be reserved for situations where collaboration has failed or where authority beyond the PM's level is genuinely required. The scenario provides no indication that collaboration has been attempted or exhausted.
**Why not A:** Escalating immediately to the executive sponsor bypasses the PM's responsibility to facilitate collaborative resolution. No attempt has been made to bring the two stakeholders together to explore creative solutions, and escalation should be reserved for situations where the PM's facilitation has been exhausted.
**Why not B:** Following the operations director's priority simply because of the holiday deadline takes sides without exploring whether both objectives can be satisfied. The PM should not default to one stakeholder's priority without facilitating a conversation about alternatives such as phased deployment or parallel testing.
**Why not D:** Deferring to the QA Manager because organizational policy requires testing protocols also takes sides. While quality requirements are legitimate, so is the business deadline. The PM should help both parties explore options rather than choosing one constraint as automatically superior to the other.
Key Concept
This question covers Evaluate engagement needs for stakeholders under Collaborate with Stakeholders (People).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions