CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 39 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Educate the product owner on sprint commitment — changes should go into the backlog for the next sprint, not be injected mid-sprint
Explanation
Mid-sprint interference by the product owner (adding items or changing priorities) disrupts team flow and undermines the sprint commitment. The Scrum Master should educate the PO on sprint stability: the sprint backlog is locked for the sprint duration; new items or priority changes go into the product backlog for consideration in the next sprint planning. This protects team focus while ensuring new priorities are not ignored.
**Why not A:** Extending the sprint length does not address the root cause — the product owner's behavior — it merely creates a larger window during which mid-sprint interference can continue to occur. Sprint length should be set based on what enables the best feedback cycle for the team, not as a coping mechanism for process violations.
**Why not B:** Escalating to senior management should be a last resort after direct coaching and process correction have been attempted and failed. The Scrum Master's primary responsibility is to coach the team and stakeholders on agile principles; bypassing that coaching role prematurely is unlikely to change behavior and can damage the working relationship between the PO and team.
**Why not C:** Requiring the team to work overtime to absorb mid-sprint additions normalizes scope creep and sets a damaging precedent. It punishes the team for the product owner's process violation, degrades sustainable pace — a foundational agile principle — and signals that sprint commitments are meaningless constraints rather than professional agreements.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).