CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 48 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Low — when changes can be incorporated without prohibitive rework cost, adaptive iteration is most effective
Explanation
Adaptive approaches assume that the cost of change can be kept relatively low by working in small increments, maintaining clean code/design, and having short feedback cycles. When changes are cheap (as in software where a line of code can be changed without demolishing a building), iterative refinement is practical. When changes are expensive (as in physical construction), the cost-of-change curve favors upfront specification.
**Why not A:** Contractual obligations can shape how changes are approved and paid for, but they do not determine whether adaptive iteration is practical. The deciding factor is how much rework a change actually requires, which depends on the nature of the product and the work.
**Why not B:** The cost of change is rarely constant across a project; it typically rises as work progresses and decisions become embedded in the product. Adaptive approaches are most valuable when that cost stays low enough for frequent changes to remain practical.
**Why not C:** When the cost of change is high, frequent iteration produces expensive rework. High change costs favor upfront specification and a predictive approach, not adaptive iteration.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).