CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 61 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

A team is using adaptive methods for a complex defense project. The customer is a government agency that requires monthly status reports in a prescribed format, formal deliverable acceptance with signatures, and compliance documentation. Can adaptive methods be used?
Show answer & explanation

Correct answer: Yes — adaptive methods govern HOW the team works internally; compliance reporting, formal acceptance, and documentation requirements can be fulfilled at deliverable and reporting points without compromising adaptive internal practices

Explanation

Compliance requirements and adaptive methods operate at different levels. Adaptive practices govern how the team works day-to-day (sprints, standups, retrospectives). Government compliance requirements define what outputs must be produced (reports, acceptance documents). A team can work adaptively internally while producing the required formal outputs at required intervals. The compliance framework and the development approach are separable.

**Why not A:** Formal government approval of the team's internal development approach is not a precondition. The agency's requirements concern outputs—monthly reports, signed acceptance, and compliance documentation—not how the team organizes its day-to-day work.

**Why not B:** Compliance requirements define what must be produced, not how the work is done. Prescribed reports, formal acceptance, and compliance documentation can all be produced at defined reporting and delivery points while the team works adaptively internally.

**Why not D:** Formal acceptance signatures can be obtained when each deliverable is accepted; they do not require a predictive waterfall lifecycle. The team can produce the required acceptance records at deliverable points without abandoning its adaptive internal practices.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).