CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 46 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

The Agile Manifesto was created by:
Show answer & explanation

Correct answer: A group of 17 software practitioners who gathered to discuss lightweight development methods in 2001

Explanation

The Agile Manifesto was written in February 2001 by 17 software practitioners (including Kent Beck, Jeff Sutherland, Ken Schwaber, and others) at the Snowbird, Utah ski resort. They gathered to discuss and align on lightweight, collaborative approaches to software development that contrasted with the heavyweight, documentation-heavy methods of the time.

**Why not A:** The Scrum Alliance did not create the Agile Manifesto; it is an organization established later to promote Scrum. The manifesto came from an informal meeting of 17 independent practitioners, not from an organization's industry research.

**Why not B:** PMI did not author the Agile Manifesto. PMI later embraced agile approaches (for example, through the Agile Practice Guide and the PMI-ACP certification), but the manifesto was written independently by software practitioners.

**Why not C:** ISO is a formal standards body and had no role in creating the Agile Manifesto, which is an informal statement of values and principles written by practitioners, not an international standard.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).