CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 79 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Upfront planning with well-defined scope, schedule, and cost from the start
Explanation
The predictive life cycle is characterized by comprehensive upfront planning where scope, schedule, and cost are determined early in the project. This contrasts with adaptive life cycles (high flexibility), iterative (repeated cycles), and incremental (frequent partial deliveries) life cycles.
**Why not A:** Frequent delivery of deliverables throughout the project describes an incremental life cycle, not a predictive one. Predictive projects deliver the final product at or near the end of the project, not in frequent partial deliveries during execution.
**Why not C:** Daily customer involvement in development decisions is a hallmark of adaptive (agile) life cycles, where customer collaboration drives iterative refinement. Predictive life cycles involve stakeholders primarily during requirements gathering and formal reviews, not daily development decisions.
**Why not D:** Flexibility to change direction based on retrospectives characterizes an adaptive or agile life cycle. Predictive life cycles resist change once planning is complete and do not use retrospectives as a mechanism for redirecting project work.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).