CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 71 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The project is expected to exceed its budgeted cost
Explanation
EAC (Estimate at Completion) represents the expected total cost of the project based on current performance. When EAC > BAC (Budget at Completion), the project is forecasted to overrun its budget. This is a critical warning signal that requires management attention and corrective action to either find cost savings or obtain additional funding authorization.
**Why not A:** If EAC is significantly higher than BAC, this indicates cost overruns are expected, not faster completion of remaining work. An EAC exceeding BAC reflects unfavorable cost performance, not schedule acceleration.
**Why not B:** An EAC higher than BAC means the project will cost more than originally budgeted, which is the opposite of performing better on cost. Better-than-planned cost performance would produce an EAC lower than BAC.
**Why not C:** EAC compared to BAC is a cost metric, not a schedule metric. Being ahead of schedule would be indicated by SPI > 1.0 or positive SV, not by the relationship between EAC and BAC.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free