Skip to content
CAPMMedium

CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

Question 71 of 85 in Explain when it is appropriate to use a predictive, plan-based approach

Pick an answer below — you'll get the explanation instantly, no signup.

A predictive project is 75% complete. The project manager calculates the Estimate at Completion (EAC) and finds it is significantly higher than the Budget at Completion (BAC). What does this indicate?
Show answer & explanation

Correct answer: The project is expected to exceed its budgeted cost

Explanation

EAC (Estimate at Completion) represents the expected total cost of the project based on current performance. When EAC > BAC (Budget at Completion), the project is forecasted to overrun its budget. This is a critical warning signal that requires management attention and corrective action to either find cost savings or obtain additional funding authorization.

**Why not A:** If EAC is significantly higher than BAC, this indicates cost overruns are expected, not faster completion of remaining work. An EAC exceeding BAC reflects unfavorable cost performance, not schedule acceleration.

**Why not B:** An EAC higher than BAC means the project will cost more than originally budgeted, which is the opposite of performing better on cost. Better-than-planned cost performance would produce an EAC lower than BAC.

**Why not C:** EAC compared to BAC is a cost metric, not a schedule metric. Being ahead of schedule would be indicated by SPI > 1.0 or positive SV, not by the relationship between EAC and BAC.

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free