CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

Question 10 of 85 in Explain when it is appropriate to use a predictive, plan-based approach

Pick an answer below — you'll get the explanation instantly, no signup.

A pharmaceutical company is developing a new drug that must comply with FDA regulations. Which project management approach is MOST appropriate?
Show answer & explanation

Correct answer: Predictive, because regulatory compliance requires detailed documentation, formal validation, and stage-gate approvals

Explanation

FDA-regulated pharmaceutical projects require extensive documentation, formal validation protocols, defined approval gates, and audit trails — all characteristics of predictive methodology. While clinical trials involve uncertainty, the overall project framework must be predictive to meet regulatory requirements. (Note: Some companies do use hybrid approaches, but pure predictive is most aligned with FDA requirements.)

**Why not A:** While a product owner can represent requirements in Scrum, FDA regulatory compliance demands extensive formal documentation, stage-gate approvals, and audit trails that go beyond what Agile Scrum naturally provides. The regulatory framework demands predictive rigor.

**Why not C:** While clinical trials do involve unknowns, the overall pharmaceutical project framework requires strict documentation, formal validation protocols, and defined approval gates. These regulatory demands outweigh the argument for adaptive methodology.

**Why not D:** While some companies experiment with hybrid approaches, the question asks which is MOST appropriate. The regulatory requirements for formal documentation, validation, and stage-gate approvals make a pure predictive approach the most natural and compliant fit.

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).