CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 58 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Assessing the impact, determining if a baseline change is needed, and processing through change control if so
Explanation
In predictive project management, schedule changes must be assessed for their impact on the overall project. If the delay affects the critical path or requires a baseline change, it must go through integrated change control. The project manager should not unilaterally change baselines or extend the project end date without formal approval.
**Why not A:** Adjusting the plan informally and distributing an updated schedule bypasses change control. In a predictive environment, all schedule changes — especially those affecting baselines — must go through the formal change management process, not informal adjustments.
**Why not B:** Immediately extending the project end date is premature. A single task delay may or may not affect the end date depending on whether the task is on the critical path and how much float it had. The impact must be assessed before any end date change is considered.
**Why not D:** Requiring the team to work extra hours to absorb the delay is an immediate reaction that skips proper analysis. The project manager should first assess the impact of the delay on the critical path and downstream activities before determining whether overtime or other corrective actions are appropriate.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).