CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 4 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Developing a new mobile app for a market segment with rapidly changing preferences
Explanation
A mobile app for a rapidly changing market requires flexibility to adapt to evolving user needs and preferences — characteristics better suited to an adaptive (agile) approach. The other examples have stable, well-defined requirements making them good candidates for predictive methodology.
**Why not A:** Building a residential home according to pre-approved architectural drawings has well-defined requirements, sequential construction phases, and regulatory compliance needs — all strong indicators for a predictive approach. The drawings define scope upfront, making predictive planning effective.
**Why not B:** Installing a well-understood enterprise software system following a standard protocol has stable, documented requirements and a proven installation process. These characteristics make it a strong candidate for predictive methodology.
**Why not C:** Constructing a bridge with detailed engineering specifications has clearly defined requirements, sequential work phases, and regulatory constraints. Bridge construction follows established engineering processes that align perfectly with predictive project management.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).