CAPMMedium
CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
A project manager is choosing between predictive and adaptive approaches for a construction project. The project has fully engineered drawings, fixed legal contracts, and regulatory permit requirements. Which approach is MOST appropriate?
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free