CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 6 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Predictive, because the project has defined requirements, regulatory constraints, and contractual obligations
Explanation
Fully engineered drawings, fixed legal contracts, and regulatory requirements are all indicators of a predictive approach. The scope is defined, change is costly and controlled, and compliance requires documentation and formal approvals — all characteristics that favor predictive methodology.
**Why not A:** Construction projects with fully engineered drawings do not inherently benefit from iterative planning. The requirements are already defined in the drawings, and physical construction work cannot be easily iterated — you cannot pour a foundation differently each sprint.
**Why not C:** A hybrid approach implies some flexibility for adaptive elements, but with fully engineered drawings, fixed contracts, and regulatory permits, there is little room or need for adaptive methods. The regulatory approval phases require formal documentation and structured processes, not flexibility.
**Why not D:** While construction involves daily physical work, this does not make it adaptive. Daily variability in construction is managed through predictive project controls — schedule updates, resource management, and risk responses — not through iterative methodology cycles.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).