Skip to content
CAPMEasy

CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

Question 54 of 85 in Explain when it is appropriate to use a predictive, plan-based approach

Pick an answer below — you'll get the explanation instantly, no signup.

Which of the following represents a key input to selecting a predictive approach?
Show answer & explanation

Correct answer: The degree of certainty and stability in the project's requirements

Explanation

The primary driver for methodology selection is the nature of the project's requirements. High certainty and stability in requirements favor predictive. High uncertainty and expected evolution favor adaptive. Team preferences, PM experience, and tooling are secondary considerations that should adapt to the project's characteristics, not drive methodology selection.

**Why not A:** Team preference is a secondary consideration, not a key input to methodology selection. The methodology should be driven by project characteristics — particularly requirement certainty and stability — not by what the team prefers to use.

**Why not B:** The project manager's years of experience may influence their comfort level with a methodology but should not drive the selection. An experienced PM should be able to apply whichever methodology best fits the project's characteristics, regardless of personal experience.

**Why not D:** Whether the organization uses project management software is a tooling consideration, not a methodology selection input. Both predictive and adaptive approaches can be supported by various software tools. The tool does not determine the methodology.

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free