CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

Question 74 of 85 in Explain when it is appropriate to use a predictive, plan-based approach

Pick an answer below — you'll get the explanation instantly, no signup.

An organization has used a predictive methodology successfully for years. A new project manager, trained in agile, joins and argues that the organization should switch to Scrum for all projects because it is 'more modern.' How should the organization respond?
Show answer & explanation

Correct answer: Evaluate each project on its characteristics; predictive should be used for projects where requirements are stable and well-defined, and adaptive for projects with high uncertainty

Explanation

Methodology selection should be based on project characteristics, not organizational tradition or personal preference. Projects with stable requirements benefit from predictive; projects with high uncertainty benefit from adaptive. A thoughtful response evaluates the portfolio: some projects may genuinely benefit from agile approaches, while others (infrastructure, regulatory compliance, established processes) are better served by predictive methods.

**Why not A:** Rejecting the proposal outright based on tradition alone is not a sound management response. While the organization has successful processes, it should evaluate whether some projects might benefit from different approaches rather than dismissing new ideas categorically.

**Why not C:** Letting each project manager choose methodology based on personal preference lacks organizational governance. Methodology selection should be driven by project characteristics, organizational requirements, and stakeholder needs — not individual preference. This approach could lead to inconsistent practices and suboptimal choices.

**Why not D:** Switching all projects to Scrum immediately based on one person's advocacy is reckless. Many of the organization's projects may have characteristics (stable requirements, regulatory compliance, fixed contracts) that are well-served by predictive approaches. A wholesale switch without evaluation would likely harm project outcomes.

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).