CAPM Practice: Explain the components of an adaptive plan

Question 56 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

What does 'cone of uncertainty' imply for early estimates in adaptive project planning?
Show answer & explanation

Correct answer: Early estimates have high uncertainty; plans should accommodate the wide range of possible outcomes and refine estimates as learning occurs

Explanation

The cone of uncertainty shows that early estimates can be off by 4x or more in either direction. Adaptive planning accounts for this by treating early estimates as rough guidance, refining them iteratively as the team learns more.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).