CAPM Practice: Explain the components of an adaptive plan

Question 1 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive plan differs from a predictive plan primarily in that it:
Show answer & explanation

Correct answer: Plans in detail only for the near term and at a high level for the future, with the plan evolving as more is learned

Explanation

Adaptive planning is progressive and iterative. Near-term work (the next sprint) is planned in detail. Future work is planned at a higher level and refined as understanding grows. This 'rolling wave' of planning reflects the reality that detailed plans for distant future work are often wrong, since conditions and understanding change. The plan evolves alongside growing knowledge.

**Why not B:** Adaptive projects are not unplanned. Planning happens continuously — at the release, iteration, and daily levels — rather than all at once up front. The difference is in when and how detailed the planning is, not whether planning occurs.

**Why not C:** Creating a comprehensive plan at the start describes a predictive approach, not an adaptive one. Even predictive plans are not frozen; they are updated through change control. Adaptive plans deliberately evolve as the team learns more.

**Why not D:** Adaptive planning is collaborative. The product owner prioritizes the backlog, but the team participates in planning, estimates the work, and determines how much it can commit to. Planning without team input contradicts agile principles of self-organizing teams.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).