CAPM Practice: Explain the components of an adaptive plan

Question 7 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team's sprint plan includes user stories with estimated story points. The team then creates tasks for each story during sprint planning. These tasks differ from story points in that:
Show answer & explanation

Correct answer: Tasks are the specific 'how' activities the team will perform to complete each story, typically estimated in hours

Explanation

During sprint planning's second part, the team decomposes user stories into specific tasks — the concrete work activities needed to implement the story. Tasks are typically estimated in hours or days (not story points) and are visible on the sprint board. Stories represent the 'what' (what the user needs); tasks represent the 'how' (what technical steps will be taken).

**Why not A:** This reverses the relationship. Stories are estimated in story points (a relative measure of size and complexity), while tasks are typically estimated in hours.

**Why not B:** The product owner owns the product backlog and the priority of its stories, but tasks are created and owned by the team, which decides how the work will be done.

**Why not C:** Tasks are created in the sprint backlog to complete specific stories during the sprint; they are not permanent backlog items. Stories do not expire either — unfinished stories return to the product backlog to be reprioritized.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).