CAPM Practice: Explain the components of an adaptive plan
Question 31 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A completed product increment that meets the Definition of Done and could be released if the product owner decides to
Explanation
A potentially shippable increment is the output of each iteration — it meets the Definition of Done and is of release quality. The product owner decides whether to actually release it. This gives business maximum flexibility.
**Why not A:** Potentially shippable does not mean shipped to all customers every iteration.
**Why not C:** Regulatory approval is not part of the definition.
**Why not D:** A feedback prototype is not a release-quality increment meeting the Definition of Done.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).