CAPM Practice: Determine how to prepare and execute task management steps

Question 4 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team uses a physical task board. Mid-sprint, a team member notes that their task has been 'In Progress' for 4 days but is not complete. What should the Scrum Master investigate?
Show answer & explanation

Correct answer: Whether the task is too large, has hidden dependencies, or the team member is blocked — then take appropriate action to resolve

Explanation

A task stuck 'In Progress' for multiple days signals a potential problem: the task may be larger than estimated (needs splitting), there may be hidden dependencies (blocked waiting on someone else), the team member may be struggling (needs technical help or pairing), or an impediment has emerged. The Scrum Master investigates the specific cause and facilitates the appropriate response to restore flow.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).