CAPM Practice: Determine how to prepare and execute task management steps

Question 39 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

What is the primary purpose of the daily standup (daily Scrum) in managing iteration tasks?
Show answer & explanation

Correct answer: To synchronize the team, inspect progress, and adapt the day's plan to meet the iteration goal

Explanation

The daily standup synchronizes team members — sharing what's done, what's next, and what's blocked. It's the team's daily inspect-and-adapt event, not a status report. It enables real-time collaboration and impediment resolution.

**Why not A:** The daily standup is not a detailed status update to the project manager. It is the team's own synchronization and planning event, focused on progress toward the iteration goal.

**Why not B:** The standup is not meant to single out team members who are behind on individual commitments. It focuses on the team's collective progress and on surfacing impediments so the team can help one another.

**Why not D:** Re-estimating all remaining tasks and updating a schedule baseline is not the purpose of the daily standup. It is a short, time-boxed event to synchronize the team and adapt the day's plan, not a formal re-planning or baseline update.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).