CAPM Practice: Determine how to prepare and execute task management steps

Question 54 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

A team's task board shows many tasks are 'In Progress' simultaneously with very few moving to 'Done.' What is the likely root cause and solution?
Show answer & explanation

Correct answer: WIP limits may be too high or absent, causing multitasking. Reducing WIP and focusing on completing tasks will improve flow

Explanation

Many in-progress items with few completions indicates multitasking and context-switching overhead. The fix is reducing WIP — either via explicit limits or team agreements — and focusing on completing items before starting new ones.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).