CAPM Practice: Determine how to prepare and execute task management steps
Question 54 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: WIP limits may be too high or absent, causing multitasking. Reducing WIP and focusing on completing tasks will improve flow
Explanation
Many in-progress items with few completions indicates multitasking and context-switching overhead. The fix is reducing WIP — either via explicit limits or team agreements — and focusing on completing items before starting new ones.
**Why not A:** Adding more tasks to keep everyone busy increases work in progress, which worsens multitasking and context switching. The goal is to finish work, not to maximize individual utilization.
**Why not C:** Relaxing the Definition of Done would lower quality without addressing the real cause. Items are stalling because too many are started at once, not because the completion standard is too strict.
**Why not D:** Adding more items to the sprint backlog does nothing to help in-progress work reach 'Done.' It adds to the pile of unfinished work rather than improving flow.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).