CAPM Practice: Determine how to prepare and execute task management steps
Question 43 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Adopt a workflow where testing is done continuously as each story is developed, not batched at the end
Explanation
End-of-iteration testing crunches are an anti-pattern. The fix is continuous testing — developers and testers work on each story together, with testing done before the story is marked done. This keeps quality concerns from compounding.
**Why not A:** Reducing the number of stories may shrink the crunch, but testing is still batched at the end of the iteration. This treats the symptom rather than the workflow problem that causes it.
**Why not B:** Adding testers for the last few days reinforces the batching anti-pattern and adds handoffs. The root cause — testing deferred until the end of the iteration — remains.
**Why not C:** Extending iterations delays feedback and gives the team more time to accumulate untested work. The crunch simply moves to the end of a longer iteration.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).