Question 1 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

In adaptive project management, work-in-progress (WIP) limits are used to:
Show answer & explanation

Correct answer: Limit the number of items being worked on simultaneously to improve flow and reduce context switching

Explanation

WIP limits constrain how many items can be in any given workflow state simultaneously (e.g., only 3 items can be 'In Progress' at once). This prevents multitasking, reduces context switching, surfaces bottlenecks when upstream items pile up waiting for a congested state, and encourages team members to help complete in-progress items rather than starting new ones. WIP limits improve flow efficiency.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).