CAPM Practice: Determine how to prepare and execute task management steps

Question 7 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

In Kanban, 'pull' refers to:
Show answer & explanation

Correct answer: Team members pulling the next highest-priority item from the backlog when they have capacity, rather than having work pushed onto them

Explanation

Kanban is a pull system: work is pulled by team members when they have capacity — they select the next highest-priority item that fits within WIP limits. This contrasts with push systems where managers assign work regardless of capacity. Pull systems respect team capacity, reduce multitasking, and allow natural flow regulation based on actual throughput.

**Why not B:** Removing low-value items from the backlog is backlog refinement, not the Kanban pull concept. In Kanban, 'pull' describes how team members take on new work only when they have capacity, not how items are pruned from the backlog.

**Why not C:** Accepting whatever tasks a manager assigns is a push system, the opposite of pull. Kanban's pull approach lets team members select the next highest-priority item when capacity frees up, within WIP limits.

**Why not D:** Pulling code from a repository is a version control action, not a Kanban workflow concept. In Kanban, 'pull' refers to how work items move through the system based on available capacity.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).