CAPM Practice: Determine how to prepare and execute task management steps
Question 10 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The team (or the Scrum Master during review) should enforce DoD criteria and move the card back to the appropriate state for the missing work
Explanation
The Definition of Done is non-negotiable — it's a quality gate, not a suggestion. If a card is moved to 'Done' without meeting DoD criteria, it must be moved back to 'In Progress' (or appropriate state) and the missing work completed. Allowing DoD exceptions sets a precedent that DoD can be bypassed, eroding quality standards and creating technical debt.
**Why not A:** A team member declaring a card complete does not make it done. The DoD exists so that completion is judged against shared, explicit criteria rather than individual opinion; accepting the card would count unfinished work as complete.
**Why not B:** Treating partial DoD completion as a normal exception undermines the DoD as a quality gate. Once exceptions become routine, the team loses a shared understanding of what 'Done' means and hidden work accumulates.
**Why not D:** Deferring the missing DoD items to a later sprint means the card is reported as done while work remains, which misrepresents progress and creates technical debt. The card should return to the appropriate state until all DoD criteria are met.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).