CAPM Practice: Determine how to prepare and execute task management steps
Question 12 of 60 in Determine how to prepare and execute task management steps
Show answer & explanation
Correct answer: The team exhibits 'late sprint heroics' — stories are being completed just before the sprint ends rather than consistently throughout, suggesting stories are too large, WIP is too high, or the team is working on partial stories rather than completing one at a time
Explanation
'Late sprint heroics' — normal flat burndown followed by steep completion near sprint end — typically indicates: stories are too large (completed near end because they take the full sprint), or the team is working on many stories simultaneously without completing any (high WIP, then multiple stories complete simultaneously at sprint end). The fix: split stories to be smaller (completable in 1-3 days), enforce WIP limits to encourage completion before starting new work, and monitor mid-sprint progress more actively.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free