CAPM Practice: Determine how to prepare and execute task management steps

An adaptive team's sprint burndown chart shows that after 5 days of a 10-day sprint, they have completed only 20% of their story points (should be ~50%). The burndown is much steeper in the last few days of past sprints. What is the MOST likely cause and what should the Scrum Master address?

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).