CAPM Practice: Determine how to prepare and execute task management steps

Question 49 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

How do agile teams typically handle unplanned work that emerges during an iteration?
Show answer & explanation

Correct answer: Evaluate urgency — truly urgent work may displace planned items (with product owner input), while non-urgent work goes to the backlog

Explanation

Unplanned work should be triaged: urgent issues may displace lower-priority planned work (with product owner agreement), while non-urgent items go to the backlog for future planning. This balances commitment with responsiveness.

**Why not A:** Adding work without adjusting anything else overloads the team and undermines the iteration commitment.

**Why not C:** Ignoring new information regardless of urgency contradicts agile responsiveness.

**Why not D:** Pushing work onto individuals' own time hides it, is unsustainable, and bypasses prioritization.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).