CAPM Practice: Determine how to prepare and execute task management steps
Question 57 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Teams identify dependencies during planning, visualize them on the task board, and communicate proactively — resolving or sequencing dependent tasks to maintain flow
Explanation
In agile, dependencies are managed through transparency and communication. Task boards can show dependencies visually; daily standups surface blocked tasks; the team collectively solves dependencies through collaboration, resequencing, or helping each other complete prerequisite work.
**Why not A:** Dependency management is a shared team responsibility in agile. Handing dependencies to the project manager to track and resolve removes ownership from the people doing the work and slows resolution; the team surfaces and manages dependencies itself, with the project manager helping remove impediments.
**Why not B:** Self-organization does not make dependencies disappear. Ignoring them leads to blocked tasks and interrupted flow; self-organizing teams make dependencies visible and resolve them collaboratively.
**Why not C:** Assigning all dependent tasks to one team member creates bottlenecks and single points of failure, and is often impractical given the different skills tasks require. Agile teams instead manage dependencies through visibility, sequencing, and helping each other complete prerequisite work.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).