CAPM Practice: Determine how to prepare and execute task management steps
Question 32 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Delaying irreversible decisions (like technology choices within a task) until sufficient information is available to decide wisely
Explanation
Applied to task execution, last responsible moment means deferring irreversible choices (technology selection, implementation approach) within a task until enough information is known to make a good decision, reducing costly rework.
**Why not A:** The principle applies to decisions, not to completing work at the deadline, which only increases schedule risk.
**Why not B:** Starting every task as late as possible removes float; the principle is about deferring irreversible decisions, not task start dates.
**Why not D:** Waiting until low-priority tasks become urgent is reactive prioritization, not deferring decisions until enough information exists.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free