CAPM Practice: Determine how to prepare and execute task management steps
Question 16 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitate a discussion about the DoD and acceptance criteria; stories that don't meet acceptance criteria are NOT done and should not be accepted, regardless of 'good enough' language
Explanation
Accepting work that doesn't meet defined acceptance criteria undermines quality standards and the Definition of Done. The Scrum Master should facilitate a clear conversation: are the acceptance criteria wrong (and need updating) or is the work incomplete (and needs to return to the backlog)? If criteria were wrong, update them and check the work against updated criteria. If work is incomplete, it returns to the backlog — not masked as 'good enough.'
**Why not A:** The product owner does decide on acceptance, but that authority operates within the agreed acceptance criteria and Definition of Done. Accepting stories that don't meet them misrepresents progress and hides incomplete work, so the Scrum Master should not simply defer.
**Why not B:** Removing acceptance criteria after the fact just to allow acceptance hides the real gap and erodes transparency and quality standards. If the criteria were genuinely wrong, they should be revisited openly with the team — not deleted to make incomplete work look done.
**Why not D:** Treating the stories as accepted and planning remediation later creates hidden technical debt and inflates reported progress. Incomplete stories should return to the backlog for the product owner to reprioritize, not be counted as done with a follow-up fix.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).