Question 16 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A team consistently overestimates story points during planning, resulting in many uncommitted items each sprint. What is the MOST useful corrective action?
Show answer & explanation

Correct answer: Review estimation accuracy after each sprint and recalibrate using actual data to improve future estimates

Explanation

Consistently over-estimating indicates a calibration problem. The team should review completed stories and their actual effort compared to their estimates, looking for patterns (always over-estimate complex stories? Always under-estimate UI work?). This retrospective calibration improves future estimates empirically. Blanket percentage adjustments ignore the root cause of estimation error.

**Why not A:** Switching to hour-based estimates does not solve a calibration problem — it changes the unit of measurement without addressing the team's underlying tendency to misjudge complexity. Story points are intentionally abstract to capture uncertainty and relative effort; hours encourage false precision and can anchor discussions to task execution time rather than overall complexity.

**Why not C:** Applying a blanket 20% reduction treats all overestimates uniformly and ignores the patterns behind the errors. It also trains the team to adjust numbers mechanically rather than developing genuine estimation judgment through reflection on what caused the gap between estimate and actuality.

**Why not D:** Designating a single estimator removes the diversity of perspectives that makes team estimation accurate and buy-in high. Estimation skill develops through collective reflection and calibration against real delivery data; centralizing it in one person concentrates the bias of that individual and eliminates the cross-functional insights that improve forecast quality over time.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).