CAPM Practice: Determine how to plan project iterations
Question 24 of 61 in Determine how to plan project iterations
Show answer & explanation
Correct answer: Accounting for team member availability (after deducting holidays, meetings, and other commitments) to determine realistic working hours per sprint
Explanation
Realistic capacity planning accounts for: planned holidays/PTO during the sprint; recurring meetings (standup, planning, review, retrospective); other commitments (training, organizational meetings). Net available hours — not gross calendar time — determine how much work the team can realistically accomplish. This prevents overcommitment based on unrealistic capacity assumptions.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free