CAPM Practice: Determine how to plan project iterations
Question 24 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Accounting for team member availability (after deducting holidays, meetings, and other commitments) to determine realistic working hours per sprint
Explanation
Realistic capacity planning accounts for: planned holidays/PTO during the sprint; recurring meetings (standup, planning, review, retrospective); other commitments (training, organizational meetings). Net available hours — not gross calendar time — determine how much work the team can realistically accomplish. This prevents overcommitment based on unrealistic capacity assumptions.
**Why not A:** Previous velocity is a useful reference point, but using it without adjustment ignores changes in availability for the upcoming sprint, such as holidays, PTO, or training. If availability drops, an unadjusted velocity figure leads to overcommitment.
**Why not C:** Multiplying team members by sprint days produces gross calendar time, not realistic capacity. It ignores holidays, recurring meetings, and other commitments that reduce the hours actually available for sprint work.
**Why not D:** Adding an arbitrary 20% buffer to the previous sprint's story points inflates capacity without any basis in actual availability. This encourages overcommitment rather than preventing it.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).