In adaptive projects, team capacity for sprint planning is calculated by:
Show answer & explanation

Correct answer: Accounting for team member availability (after deducting holidays, meetings, and other commitments) to determine realistic working hours per sprint

Explanation

Realistic capacity planning accounts for: planned holidays/PTO during the sprint; recurring meetings (standup, planning, review, retrospective); other commitments (training, organizational meetings). Net available hours — not gross calendar time — determine how much work the team can realistically accomplish. This prevents overcommitment based on unrealistic capacity assumptions.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).