CAPM Practice: Determine how to plan project iterations

Question 19 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A product owner and development team disagree on the sprint goal. The PO wants to focus on a new feature; the team argues that technical debt from the last sprint must be addressed first or future velocity will suffer. How should this be resolved?
Show answer & explanation

Correct answer: The team's technical judgment should be respected; a sprint goal that balances the new feature with technical debt remediation serves both business and technical sustainability

Explanation

This scenario illustrates the tension between business features and technical sustainability. The product owner manages business priorities; the development team manages technical integrity. A healthy Scrum team negotiates sprint goals that balance both. Teams that continuously ignore technical debt accumulate slow-down that ultimately harms business value delivery. A thoughtful sprint goal might include: 'Deliver the core of the new feature while remediating the technical debt that's blocking future velocity' — making both concerns explicit.

**Why not A:** A mechanical 50/50 split treats the feature and the technical debt as two separate goals competing for capacity rather than one negotiated sprint goal. The right balance depends on how severely the debt is blocking future work and on the value of the feature, which the PO and team should agree on together instead of applying an arbitrary formula.

**Why not B:** The Scrum Master is a servant leader who facilitates the conversation between the product owner and the team. The Scrum Master does not have authority to decide product or technical priorities on the team's behalf.

**Why not D:** Although the product owner owns and orders the backlog, the sprint goal is crafted collaboratively by the whole Scrum team, and the developers are accountable for technical quality. Overriding the team's warning about technical debt would slow future velocity and ultimately harm business value.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).