CAPM Practice: Determine how to plan project iterations

Question 49 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What is 'backlog refinement' and why is it important for iteration planning?
Show answer & explanation

Correct answer: The ongoing process of adding detail, estimates, and priority to backlog items to make them ready for iteration planning

Explanation

Backlog refinement (grooming) ensures items at the top of the backlog are well-understood, estimated, and appropriately sized before iteration planning. This makes iteration planning faster and more effective.

**Why not B:** Recording completed items is documentation, not preparing upcoming items for iteration planning.

**Why not C:** Agile teams self-select work; pre-assigning items to individuals is not part of refinement.

**Why not D:** Refinement adds detail and reprioritizes items; it does not purge work that has not started.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).