Question 45 of 67 in Determine how to gather requirements

Pick an answer below — you'll get the explanation instantly, no signup.

What is the purpose of conducting a 'requirements review' before development begins?
Show answer & explanation

Correct answer: To inspect requirements for quality issues — ambiguity, incompleteness, infeasibility, conflicts — while changes are still inexpensive

Explanation

Requirements reviews catch defects before they propagate into design and code. Finding and fixing a requirements error before development is exponentially cheaper than discovering it during testing or production — a fundamental principle of quality management.

**Why not B:** Obtaining management approval for the project to proceed is a governance gate decision, not the purpose of a requirements review. While review results may inform go/no-go decisions, the review itself focuses on inspecting requirements quality to find and fix issues before development begins.

**Why not C:** Assigning each requirement to a specific developer is a work allocation activity done during sprint planning or development planning, not during a requirements review. The review focuses on identifying quality issues in requirements, not on distributing implementation responsibilities.

**Why not D:** Finalizing the project budget based on the number of requirements is a cost estimation activity. Requirements reviews focus on quality inspection to catch ambiguity, incompleteness, and conflicts while changes are still inexpensive, not on deriving budget figures from requirements counts.

Key Concept

This question covers Determine how to gather requirements under Determine how to gather requirements (Business Analysis Frameworks).