CAPM Practice: Determine how to gather requirements
Question 12 of 67 in Determine how to gather requirements
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Workshops bring multiple stakeholders together, enabling real-time conflict resolution, group synergy, and decisions that individual interviews can't produce
Explanation
Workshops combine diverse perspectives in real time — stakeholders build on each other's ideas, conflicts surface and resolve immediately, and group consensus emerges. The synergy produces richer, more complete requirements than sequential individual interviews.
**Why not A:** While workshops may consolidate time compared to many individual interviews, cost savings is not their primary advantage. The real value lies in the interactive dynamics: stakeholders building on each other's ideas, real-time conflict resolution, and group consensus that individual sessions cannot produce.
**Why not B:** Workshops do not eliminate the need for follow-up elicitation. Complex requirements often require additional investigation, clarification sessions, or detailed analysis after the workshop. Workshops surface and align on key requirements, but they rarely capture every detail needed for implementation.
**Why not C:** Workshops are not always faster than individual interviews. They require significant preparation, scheduling coordination, and facilitation effort. Their advantage is the quality and completeness of requirements produced through group interaction, not necessarily speed of execution.
Key Concept
This question covers Determine how to gather requirements under Determine how to gather requirements (Business Analysis Frameworks).