CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 5 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Communication plan requires monthly stakeholder reports → Distribute reports on the defined schedule 2. Risk management plan identifies weekly risk reviews → Schedule and conduct regular sessions as specified 3. Quality management plan specifies peer reviews for deliverables → Implement review checkpoints before delivery 4. Resource management plan defines team skill development → Provide training opportunities per the plan
Explanation
Following planned strategies requires executing the specific actions defined in each plan: communication plans require delivering communications as scheduled, risk plans require conducting reviews as specified, quality plans require implementing defined checkpoints, and resource plans require providing planned development opportunities.
**Why not A:** This option mismatches all four strategies. Communication plan requirements should lead to distributing reports, not implementing review checkpoints. Risk reviews should lead to conducting sessions, not providing training. Quality peer reviews should lead to implementing checkpoints, not distributing reports. Resource development should lead to training, not conducting review sessions.
**Why not B:** This option swaps all four response actions incorrectly. The communication plan should lead to distributing reports, not conducting review sessions. Risk reviews should lead to regular sessions, not implementing checkpoints. Quality reviews should lead to checkpoints, not training. Resource development should lead to training, not distributing reports.
**Why not D:** This option assigns training to the communication plan and report distribution to the resource plan, which are clearly mismatched. Monthly stakeholder reports require distributing communications, not providing training. Team skill development requires training opportunities, not distributing reports.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).