CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 29 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Follow the risk management plan and escalate to the sponsor immediately
Explanation
The risk management plan is a planned strategy that specifies escalation procedures. When a high-impact risk is identified, following the documented process means escalating immediately as planned. This ensures proper governance and timely decision-making.
**Why not A:** Updating the risk register and continuing to monitor is insufficient for a high-impact risk that requires immediate escalation per the risk management plan. Passive monitoring does not meet the documented escalation requirement for this risk category.
**Why not C:** Waiting until the next steering committee meeting delays action on a critical security vulnerability. The risk management plan specifies immediate escalation for high-impact risks, and waiting for a scheduled meeting violates this planned procedure.
**Why not D:** Assigning the team to fix the vulnerability without escalation ignores the governance process documented in the risk management plan. High-impact risks require sponsor awareness and decision-making authority that the project team alone cannot provide.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).