CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 76 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Kavya Virtanen is managing an infrastructure project for Eastbound Logistics. During benefit planning, the sponsor emphasizes reducing operational costs by 15% within six months of project completion. The project team questions whether this benefit is realistic given the project scope. What should Kavya do?
Show answer & explanation

Correct answer: Facilitate a discussion with the sponsor and team to validate the benefit target against the project scope and capabilities

Explanation

Benefit planning requires realistic and achievable targets. Kavya should facilitate alignment between the sponsor's expectations and what the project can deliver by bringing both parties together to validate assumptions and adjust targets or scope as needed.

**Why not A:** Documenting the benefit target as a risk avoids the necessary discussion about whether the target is realistic. The team's concern is about feasibility, which should be addressed directly through stakeholder dialogue, not merely logged as a risk.

**Why not B:** Accepting the target without validating it against the project scope could set the team up for failure. If the 15% cost reduction is not achievable given the project deliverables, proceeding without discussion creates unrealistic expectations.

**Why not D:** Reducing the project scope to fit the benefit target puts the cart before the horse. The appropriate action is to align expectations through discussion first, then determine if scope, benefit targets, or both need adjustment based on that analysis.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).