Skip to content
CAPMMedium

CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 60 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Riku Rahimi is reviewing how to respond appropriately to different planned project strategies at Maple Ridge Corp. Match each project management plan component on the left with the appropriate execution response on the right. Items: 1. Quality Management Plan specifies peer reviews for all deliverables 2. Stakeholder Engagement Plan requires monthly sponsor briefings 3. Resource Management Plan defines team member roles and responsibilities 4. Procurement Management Plan outlines vendor selection criteria Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Quality Management Plan specifies peer reviews for all deliverables → Conduct peer review sessions before accepting any deliverable as complete 2. Stakeholder Engagement Plan requires monthly sponsor briefings → Schedule and conduct monthly meetings with the project sponsor 3. Resource Management Plan defines team member roles and responsibilities → Assign work to team members according to their defined roles in the plan 4. Procurement Management Plan outlines vendor selection criteria → Use the defined criteria to evaluate and select vendors consistently

Explanation

Following planned strategies means executing the specific activities defined in each management plan component. Quality plans require quality processes like peer reviews. Stakeholder plans require scheduled engagement activities. Resource plans guide role-based assignments. Procurement plans provide criteria for vendor decisions. Each planned strategy must be executed consistently as specified.

**Why not A:** This option mismatches all four items. Quality peer reviews are matched with resource assignments, stakeholder briefings with vendor selection, resource roles with quality reviews, and procurement criteria with sponsor meetings. None are correctly paired.

**Why not B:** This option assigns sponsor briefings to quality management, resource assignments to stakeholder engagement, vendor selection to resource management, and peer reviews to procurement. Each execution response is matched to the wrong plan component.

**Why not C:** This option correctly matches stakeholder engagement and resource management but incorrectly assigns vendor selection to quality management and peer reviews to procurement. Quality processes involve peer reviews, not vendor evaluation criteria.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free