CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 22 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Match each project initiation activity on the left with its PRIMARY purpose on the right. Items: 1. Developing the project charter 2. Identifying stakeholders 3. Documenting business case benefits 4. Defining high-level requirements Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Developing the project charter → Provides formal authorization for the project to begin 2. Identifying stakeholders → Establishes who will be affected by or can influence the project 3. Documenting business case benefits → Justifies the project investment and expected value delivery 4. Defining high-level requirements → Captures initial product or service characteristics needed

Explanation

Each initiation activity serves a distinct purpose: the charter authorizes the project, stakeholder identification maps influence and impact, the business case justifies the investment through expected benefits, and high-level requirements capture what needs to be delivered.

**Why not A:** This option reverses the purposes of the project charter and documenting business case benefits, and also swaps stakeholder identification with high-level requirements. The charter authorizes the project, not justifies investment; stakeholder identification maps people, not product characteristics.

**Why not B:** This option mismatches the charter with capturing product characteristics and high-level requirements with formal authorization. The charter's primary purpose is formal authorization, while high-level requirements capture initial product or service needs.

**Why not D:** This option incorrectly assigns stakeholder identification purposes to the charter and business case purposes to stakeholder identification. The charter authorizes the project, stakeholder identification maps who is affected, not investment justification.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).