CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 68 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. A key vendor may not deliver materials on time → Execute the risk response strategy 2. The CEO requests monthly project updates → Follow the communication management plan 3. Team productivity varies between sprints → Apply the quality management approach 4. Stakeholder expectations are unclear → Use the stakeholder engagement plan
Explanation
Vendor delivery issues require risk response execution. CEO update requests align with communication planning. Productivity variations relate to quality and process improvement. Unclear expectations require stakeholder engagement to clarify needs and manage expectations.
**Why not A:** This option mismatches all four scenarios. Quality management does not address vendor delivery issues, stakeholder engagement is not for CEO updates, risk response does not govern productivity variations, and communication plans do not address unclear expectations.
**Why not B:** This option incorrectly assigns communication planning to vendor delays and quality management to CEO updates. Vendor delivery uncertainty is a risk requiring risk response, and CEO update requests are communication management activities.
**Why not D:** This option correctly matches items 2 and 3 but incorrectly assigns stakeholder engagement to vendor delivery issues and risk response to unclear expectations. Vendor delivery risk requires a risk response strategy, not a stakeholder engagement approach, since it involves supply chain uncertainty rather than stakeholder relationships.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).