CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 72 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Business case → Justifies the project investment by documenting expected benefits and costs 2. Benefits realization plan → Documents how and when project benefits will be delivered and measured 3. Project charter → Formally authorizes the project and appoints the project manager 4. Benefits owner → Individual responsible for ensuring expected benefits are achieved
Explanation
The business case provides the economic justification for the project. The benefits realization plan outlines how benefits will be delivered and tracked throughout and after the project. The project charter formally authorizes the project and names the project manager. The benefits owner is the person accountable for ensuring the intended benefits are realized, often continuing beyond project closure.
**Why not A:** This option incorrectly assigns the business case to authorizing the project (which belongs to the project charter), the benefits realization plan to the benefits owner role, the project charter to justifying the investment (which belongs to the business case), and the benefits owner to documenting benefit delivery (which belongs to the benefits realization plan). Multiple pairings are swapped.
**Why not B:** This option incorrectly assigns the business case to documenting benefit delivery timing (which belongs to the benefits realization plan), the benefits realization plan to authorizing the project (which belongs to the charter), the project charter to the benefits owner role, and the benefits owner to justifying the investment (which belongs to the business case). All four pairings are wrong.
**Why not D:** This option incorrectly assigns the business case to the benefits owner role (which is a person, not a document purpose). While the benefits realization plan and project charter are correctly matched, misclassifying the business case's purpose and the benefits owner's definition demonstrates confusion between documents and roles.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).