Which document identifies the measurable value that a project is expected to deliver to the organization?
Show answer & explanation

Correct answer: Business case

Explanation

The business case documents the justification for the project, including the expected benefits and measurable value to be delivered. It is typically developed before the project is formally initiated and serves as an input to the project charter and benefits planning.

**Why not A:** The stakeholder register identifies individuals and groups with an interest in the project, along with their influence and engagement needs. It does not document the measurable value or expected benefits of the project investment.

**Why not B:** The risk register documents identified risks, their probability, impact, and response strategies. It tracks uncertainties that could affect the project but does not identify the measurable value the project is expected to deliver.

**Why not D:** The project management plan describes how the project will be executed, monitored, and controlled. While it references project objectives, it does not serve as the primary document justifying the investment through measurable value and expected benefits.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).